The UK sanctions 4 Georgians for Kremlin disinformation and names Tskhinvali’s leadersKazakhstan’s inflation slows to 9.3% in September as the tenge opens the week at 447.73Turkmenistan reports 6.3% growth for 9 months and a budget collected to 100.1% of planFour German party foundations stop work in Georgia after Tbilisi rejects their grants
Energy

A dawn test at the new Syrdarya plant knocks 1,600 MW off Uzbekistan’s grid, splits Kazakhstan’s north-south transit and sheds 962 MW in the south for 41 minutes

At 05:05 on Friday, during commissioning tests at the new 1,573 MW thermal plant in Bayavut district of Syrdarya region, built by the consortium of France’s EDF, Qatar’s Nebras Power and Japan’s Sojitz and Kyuden, 1,600 MW of capacity dropped out of Uzbekistan’s grid and households and farm water pumps in several regions lost power, the energy ministry said through its Telegram channel; reserves at other plants and the storage systems were brought in, every consumer was back by 07:27, and the ministry apologised, Spot reported at 07:54. Kazakhstan’s grid operator KEGOC put the loss at 1,516 MW at 05:02, said the surge of power flow split its north-south transit, restricted 962 MW of consumption, and restored the southern zone’s parallel operation with the Central Asian systems at 05:43, Forbes.kz reported.

A clean cross-section of a thick high-voltage cable in close-up, copper strands at the core and concentric rings of insulation, one ring amber.

Two operators printed two sizes for one loss, 1,600 MW in Tashkent and 1,516 in Astana, and 2 clocks 3 minutes apart, and both are the same event read from either end of a line. The plant is on test: a combined-cycle station of 1,573 MW still in commissioning, tripping during its tests, which is what commissioning is for; the grid it tripped on is the Central Asian ring, in which Uzbekistan, Kazakhstan’s south and Kyrgyzstan hang on the same frequency and Kazakhstan’s north feeds them through one transit. The surge crossed the border faster than any statement did.

Central Asia learned the mechanism on 25 January 2022, when a fault on that transit blacked out Tashkent, Almaty and Bishkek in a morning: a large block of generation falls out, the frequency drops, the flow from the north surges to fill the hole, the protection splits the transit to save the northern system, and the south is left to shed load. This time the split held 41 minutes, the shedding was 962 MW, and Uzbekistan’s restoration ran 2 hours and 22 minutes on other plants’ reserves and on the storage systems, the ministry’s phrase for the batteries it has been installing.

The surge crossed the border faster than any statement did.

What the morning measured is the size of the new plant against the ring that has to absorb it. A 1,600 MW unit removed at once by a test is the ring’s stress test as much as the plant’s; the ministry’s apology went to households and to farm pumps, the 2 loads that run at 5 in the morning in September. KEGOC’s transit split is the same mechanism as in 2022, and the answer it implies has not changed: more transit capacity, more reserve on the southern side, more batteries. The batteries were there this time. The transit was not.