Khamraev was answering Imomnazar Tursunov, a deputy of the People’s Democratic Party, who said at the Government Hour that not one soum had been spent on projects planned for 2026. The $130 million project is the reconstruction of irrigation systems in Surkhandarya, Kashkadarya, Bukhara and Namangan regions, financed by the Export-Import Bank of China.
The ministry first counted on the Chinese companies CITIC and CAMC starting the work with their own funds, the minister said, and they offered prices more than twice the estimate. Talks ran for over a year without result.
Financing then went through the bank’s procedure, with about six months of appraisal and about a year to select a contractor. CITIC won a tender among three companies at 20% above the estimate, and talks to lower the price failed, Khamraev said.
Talks with a third Chinese company, Sinohydro, were held as recently as the morning of 11 November, he said, and “the question is paused for now”. Lining of the canals is planned for 2027 to 2028. Presidential decree PP-409 of 29 November 2024 covered two projects worth $220 million in all, Gazeta.uz noted.
The $37 million modernisation of 95 pumping stations has moved from Russia to a new bank at 4% because of sanctions against Russia and higher interest rates, the minister said. The work is to be done next year.
Russian financing for pumping stations dates from decree PP-5201 of 29 July 2021, under which the state corporation VEB.RF was to lend €146 million at 2% for 10 years towards a programme of €213.5 million. The United States imposed sanctions on VEB.RF on 22 February 2022, and the decree was cancelled in December 2022.