Kremlin reports “full understanding” on its Tajik base, which Dushanbe’s account omitsKyrgyzstan makes ElCat sole operator of international internet traffic, with no end dateArmenia will publish its draft constitution on 23 November, Pashinyan tells parliamentUzbek water minister now calls 6 to 10 billion cubic metres for Qosh Tepa acceptable
Economy

Mirziyoyev opens 55 projects in Bukhara and starts 90 more worth $7.1 billion

President Shavkat Mirziyoyev commissioned 55 projects worth $654 million in Bukhara region on 3 November and launched construction of 90 more worth $7.1 billion, Gazeta.uz reported at 17:13 Tashkent time from the presidential press service. The programme of 145 projects totals $7.8 billion, and the forecast is 14,000 jobs, 22 trillion soums of annual output and $510 million of exports.

The front of a ring-spinning frame in a cotton mill fills the picture with white yarn bobbins, one of them amber.

Investors come from the United States, Canada, Germany, Japan, Korea, Singapore, China, Vietnam, Turkey, the Emirates, Saudi Arabia, Russia and India, with the Asian Development Bank and the AIIB, the press service says. “Our goal is one: to produce goods that replace imports and are in demand on foreign markets,” the president said, in Gazeta.uz’s account.

Energy is the largest block. The region has commissioned 1,000 MW of wind, 750 MW of solar and 63 MW of storage with 601 km of lines, ACWA Power’s 300 MW Bosh-2 wind farm at Gijduvan is under construction, a company Gazeta names as Toyota Corporation is building 1,000 MW of wind with Sinoma at Jondor and Peshku, and a $165 million waste-to-energy plant with Chinese partners is planned at Kagan.

Leman of Germany puts $150 million into the pumping stations of the Amu-Bukhara canal, the Kurt Baver textile complex is to process 62,000 tonnes a year, and a $400 million cotton and textile cluster with Chinese investors covers 9,000 hectares at Romitan. Two water projects worth $633 million are to reach 2 million residents, 781,000 of them for the first time, and seven road projects cost $565 million.

Tourism gets 19 large projects worth $3 billion, Mirziyoyev said, with a target of $5 billion in tourism exports from Bukhara alone. A $105 million tourism centre on 50 hectares, a $60 million congress hall and two 212-room hotels, a Hilton Garden Inn at $37 million and a Holiday Inn at $39.6 million, are among them, and Bukhara hosts the UNESCO Creative Cities conference in 2027.

The $7.8 billion is a programme figure: $654 million of it is commissioned, the rest is at the start of construction, and the press service gives no completion dates for the 90 projects.