Pashinyan ties his political future to a referendum he is six votes short of callingKazakhstan discloses court-sanctioned arrest of Samruk-Kazyna and railway chiefsRahmon discusses mining with the US deputy secretary of state on the eve of Putin’s visitJaparov meets his election rivals and warns Kyrgyz officials against working for him
Energy

Kambar-Ata-2 delivers 90 of its 120 MW because Kyrgyzstan’s lines cannot carry more

The single working unit of Kyrgyzstan’s Kambar-Ata-2 hydropower plant has delivered at most 90 MW of its 120 MW since 2010 because the transmission lines cannot carry the full output, First Deputy Energy Minister Kursantbek Omurbekov told the state station Birinchi Radio, the news agency 24.kg reported on 17 November. The country consumes about 19.6 billion kWh a year and generates about 15.5 billion.

Two bars in billion kilowatt-hours a year: about 19.6 consumed in Kyrgyzstan and about 15.5 generated at home, the gap of about 4.1 marked as imports.

That leaves 30 MW unused. Omurbekov described the country’s grids and substations as worn.

The consumption and generation figures are the energy ministry’s, and the difference is imported, 24.kg reported. The gap is about 4.1 billion kWh, or 21% of consumption, by CAW’s arithmetic.

Design work on the plant’s second unit is near completion, and construction is to start in February or March 2027 together with a 500 kV substation, Omurbekov said. The contractors and the financing were chosen earlier, he said, and the report gives no cost and no completion date.