The work is split. A terminal for 1,200 passengers an hour, with its forecourt and parking, falls to the private partner, and the state builds and runs the airfield, including a runway of 3.3 km.
The tender opened on 12 March on a build, transfer and operate model and ran in two stages, with six international companies passing the first. Spot’s report gives neither the consortium’s bid nor the partners’ shares or the source of financing.
The cost has grown. It was put at $226 million in May 2024 and at $300 million in early November, when Mirziyoyev ordered the airport finished by September 2027. That is ten months away by CAW’s arithmetic, against a construction period of up to three years in the planned agreement.
Limak runs the airports of Pristina and Dakar, took part in building Istanbul’s and is building Kuwait’s, Uzbekistan Airports said. The Qatari company was the main contractor of the Lusail stadium.