Four days after two Toktogul generators tripped and Kazakhstan's south went dark, the inquiries multiply on each side of the border and the joint one exists only in Bishkek's appeals. Kazakhstan's Tuesday cabinet session went to school readiness.

The blackout inquiry stops at the border

Tuesday brought the government's regular weekly session in Astana, the first since the 14 August failure. The six items its site posted through the day cover school construction, meal payments, medical check-ups for children, curriculum revision, harvest pace and recovered assets. None of them mentions the outage, the grid or Kyrgyzstan.

What Kazakhstan has said institutionally still dates to the day of the failure. KEGOC's 14 August statement promised that β€œthe causes of the technological disturbance will be investigated by a special commission”. Four days on, no composition, chair or deadline for that commission has surfaced in the wires and government pages this desk read.

Between those ledgers sits the body that would reconcile them.

Kyrgyzstan, for its part, investigates itself. The commission Adylbek Kasymaliev ordered on Monday sits under Azamat Apsatarov of the presidential administration's control directorate and counts a domestic ledger: 26 emergency high-voltage disconnections in 18 months. On the regional question the energy ministry has not moved: the two tripped generators at Toktogul were the initial disturbance, frequency was back at 50 hertz in 18 minutes, and assigning responsibility before a joint technical investigation finishes is, in its word, premature.

The two national timelines agree on the trigger minute and on little else. Astana's operator logs the trip at 14:37 local time and counts about 2,810 megawatts of restrictions; Bishkek logs the same minute in its own zone and counts 250 megawatts of emergency assistance it says it sent while stabilising. Between those ledgers sits the body that would reconcile them. Bishkek appeals to a joint technical investigation; no order creating one has been published by either capital.

The grids stay coupled meanwhile, which is the point. A trip at one plant ended with Almaty dark; the joint commission that would say why has not reached paper in four days. The next dated event on the file is the Apsatarov commission's output, and it reports to one capital.