The new section runs 331.84 km through Akmola region and 203.6 km through North Kazakhstan region, 535.44 km in all by CAW’s arithmetic. The report was prepared by Elkon LLP for AstanaGas KMG JSC and published in the national data bank on the state of the environment.
Building is split into three phases. Two of them lay the line and add automated gas distribution stations at Kokshetau and Petropavlovsk. A compressor station at Kokshetau and a gas metering station, Ishim, on the border with Russia come in the third.
The stages are meant to raise the capacity of the gas transport system and to supply Kokshetau, Petropavlovsk and other settlements of the two regions with Kazakh gas from western fields, routed through Kyzylorda and Astana. The document also names access to Russian gas as an aim, according to Interfax.
Gazprom and Kazakhstan signed a memorandum in October 2025 on a new trunk pipeline from Russia to Kazakhstan, running from Ishim to Astana, the agency recalled. Saryarka’s first stage, 1,061.3 km from Kyzylorda through Zhezkazgan and Karaganda to Astana, has operated since 2019.
AstanaGas KMG is owned in equal halves by the sovereign wealth fund Samruk-Kazyna and a fund of the state holding Baiterek.
Kazakhstan bought 4 billion cubic metres of gas from Gazprom in 2025 and plans 11 billion in 2026, its energy vice-minister said on 16 September. No buyer of Russian gas had been named under the US Graham sanctions act through 19 November, as CAW reported on 20 November.