Drones kill 4 in Novorossiysk and set a fuel-oil terminal alight in the port that ships Kazakhstan's oilBrent clears $100 for the first time since July, with Azeri Light at $108 against the $65 in Baku's budgetGeorgia promises to double its ports by 2032 for a corridor whose shallowest link is on the other seaRussia's defence minister tells Dushanbe the Afghan border gets special attention and its drone units get Russian help
Energy

Rosatom signs for 100 megawatts of Kyrgyz wind

Rosatom’s wind arm, the Russian-Kyrgyz Development Fund and the Eurasian Development Bank have signed for a 100 MW wind farm at Kok-Moinok in the Issyk-Kul region. The signature is five days old; the full public record of it assembled only this week.

Rosatom signs for 100 megawatts of Kyrgyz wind

The announcement travelled quietly. Rosatom’s renewables division put out the news on 6 August, Vedomosti carried it that evening, and the fullest account, from RFE/RL’s regional service, landed Monday. The signing took place during the eighth Kyrgyz-Russian economic forum on Issyk-Kul’s shore.

NovaVind Kyrgyzstan director Dmitry Andreyev signed with Artyom Novikov, chairman of the Russian-Kyrgyz Development Fund, and the Eurasian Development Bank’s deputy chairman Alexey Skatin. The site covers 200 hectares. Rosatom describes itself as developer from design through operation, runs more than 1.3 GW of wind in southern Russia and wants 2 GW by 2028.

No investment figure is attached to the new agreement. The $120 million in circulation is a project valuation from September 2024, and the financing split between the fund, the bank and the corporation is undisclosed.

The republic needs the electricity sooner than any turbine can turn.

The republic needs the electricity sooner than any turbine can turn: the energy ministry told Monday’s winter-preparation meeting it expects to import 4.1 billion kWh this year against consumption of 19.6 billion. The mid-July blackout, meanwhile, is 25 days old, and the grid operator has yet to publish a cause.

The agreement publishes a capacity and a site. The tariff, the construction calendar and who pays for what are still nowhere in the record.