Crews rebuilt the fallen tower and tested the line before it was switched on, the ministry said, with specialists from both countries working round the clock in strong wind and night frost.
L-503 ends at the Uzbekistan substation in the valley. Its loss limited supply in parts of the region, as CAW reported on 20 November, and the outage lasted about 67 hours by CAW’s arithmetic.