S&P raises Uzbekistan to BB+, one notch below investment grade, citing its GDP recountArmenia sets TRIPP launch for 23 November as US officials raise it in Baku and AshgabatUS extends licence for talks on selling Lukoil’s foreign arm to 19 DecemberTenge weakens to 455 per dollar, losing 10.7 in a week as oil falls about 6%
Energy

Power returns to the 500 kV line feeding Uzbekistan’s Fergana Valley after a tower fell

Electricity began flowing again at 01:21 local time on 22 November along L-503, the 500 kV line that carries power from Uzbekistan’s Syrdarya thermal plant to the Fergana Valley across Tajik territory, Uzbekistan’s Energy Ministry said, according to the news site Gazeta.uz. A tower on the line collapsed in bad weather on the morning of 19 November.

A pair of amber rubber insulating gloves and a spanner on the frost-covered tailgate of a utility truck.

Crews rebuilt the fallen tower and tested the line before it was switched on, the ministry said, with specialists from both countries working round the clock in strong wind and night frost.

L-503 ends at the Uzbekistan substation in the valley. Its loss limited supply in parts of the region, as CAW reported on 20 November, and the outage lasted about 67 hours by CAW’s arithmetic.