Renewables produced 8.5% of generation in the first nine months of 2026 against a plan of 7%, Ilyas said. By the end of 2035 the ministry expects at least 8.4 gigawatts of new renewable capacity, including about 1.8 gigawatts of solar. The four figures for installed capacity add up to 27.1 gigawatts, by CAW’s arithmetic, so the additions through 2029 would raise it by about half.
The month’s signed and announced projects include a 1,000 megawatt wind farm with storage in Kostanay region at $730 million, agreed at the investment round table in Shymkent on 22 October, and the 1 gigawatt data-centre valley with two supercomputers that Tokayev cited in Ankara on 30 October.
Tokayev’s Address of 28 October promised an energy surplus by 2029 and criticised electricity imports and delayed plants, Kapital recalled, naming Turkistan, Kyzylorda, Almaty and Ekibastuz. The Address set the Balkhash nuclear plant to start next year and an agreement on the Moiynkum site, and Xinhua carried Ilyas’s figures on 30 October.